Salam Gas Plant – Trains 3 & 4

(SGT3 & SGT4)   

 

Owner: Khalda Petroleum Company (KPC)

CLIENT:  Petrofac

LOCATION: Western Desert - Egypt

DESCRIPTION
 

A project calling for building 2 additional gas processing trains at Khalda Salam area in the western desert of Egypt.KPC is adding these new gas processing trains so that it can exploit the gas produced from its new discoveries at Qasr in the Khalda Concession. SGT3 and SGT4 will be gas conditioning trains encompassing gas separation, mercury removal, gas dehydration, TEG regeneration, gas dew-pointing, CO2 removal, gas export compression, condensate stabilisation, condensate storage and export system, recycle gas compression, flare system, hot oil system, power generation / distribution and all associated tie-ins with the existing plant.The total capacity of the facility with the two new trains is expected to reach 710mmcf (million cubic feet) of gas and 66,000 barrels of condensate a day by late 2008.

SCOPE OF WORK

Construction Contractor and Fabricator.

  • Fabrication and erection of static equipment
  • Erection of rotary equipment
  • Fabrication and erection of interconnecting piping
  • Fabrication and erection of tanks
  • Erection of pipe racks
  • Painting and insulation
  • Earth works
  • Concrete works
  • Installation of Electrical and Instrumentation works
  • Installation of telecommunication system
  • Onsite testing and pre-commissioning
  • Commissioning assistance
 

 

WORK VOLUME
Equipment Erection  2,905 Tons
Tanks   4 x 3,680 m 3,680 m3 Condensate tanks
Steel Structures  2,100 Tons
Carbon Steel Piping 176,636 Dia. Inch
Duplex Piping 27,000 Dia. Inch
Concrete 18,000 m3
Excavation 43,000 m3 
Backfilling 50,000 m3
E&I Cables 800 Km
Cable Trays 26 Km

 
 
 
 